Initial Management Access
Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide
113
To ground the chassis:
1
Locate the grounding point on the back of the chassis (
Figure 61
).
Figure 61: Back of BlackDiamond 8806/12804 chassis
2
Strip 0.5-inch (1.2-cm) of insulation from the stranded copper wire cable.
3
Insert the stripped wire into the cable lug.
CAUTION
Be sure that no copper is visible between the lug and the cable insulation.
4
Crimp the lug onto the cable according to the manufacturer’s specifications.
5
Insert the screws through the lug and into the grounding point on the back of the chassis.
6
Connect the other end of the wire to a known reliable earth ground point at your site.
Initial Management Access
For instructions on accessing the switch for initial management setup, see
Chapter 2, “Initial
Management Access.”
EX_128A
Grounding point
PSU
/
fan
controllers
Summary of Contents for BlackDiamond 10808
Page 14: ...Table of Contents Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 14 ...
Page 18: ...Preface Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 18 ...
Page 19: ...1 Site Preparation ...
Page 20: ......
Page 40: ...Site Preparation Extreme Networks Consolidated ExtremeXOS Hardware Installation Guide 40 ...
Page 41: ...2 BlackDiamond Switches ...
Page 42: ......
Page 93: ...3 Installing BlackDiamond Switches and Modules ...
Page 94: ......
Page 189: ...4 Installing BlackDiamond Switch Accessories ...
Page 190: ......
Page 207: ...5 BlackDiamond Maintenance Procedures ...
Page 208: ......
Page 239: ...6 Summit Family of Switches ...
Page 240: ......
Page 335: ...7 Optics ...
Page 336: ......
Page 363: ...8 Initial Management Access ...
Page 364: ......
Page 369: ...9 Appendixes ...
Page 370: ......