![Amsco Century Скачать руководство пользователя страница 63](http://html1.mh-extra.com/html/amsco/century/century_operators-manual_2936190063.webp)
6-28
129373-496
Operating Instructions
Sterilizer Operation
• Activate Seal
– Door seal fills with steam and expands against the
sterilizer door opening, forming an airtight seal.
• Purge
– Steam flows through the chamber for 1 minute.
NOTE: The projected cycle completion time shown on the display is
estimated. The control automatically evaluates the cycle progress and
corrects the estimated time at the beginning of each phase.
NOTE: Current time, chamber pressure, and chamber temperature are
printed at each transition point.
• Charge
– Chamber charges with steam to 132°C (270°F).
• Sterilize
– Sterilize phase begins when chamber temperature is equal to
or greater than 132°C (270°F). Chamber temperature is printed every 2
minutes (or printed after each programmed print interval). The steam-to-
jacket valve is regulated to maintain the chamber at 132.8°C (271°F).
Duration of sterilize phase is approximately 3-1/2 minutes.
• Fast Exhaust
– Chamber is exhausted until chamber pressure reaches 4
psig (0.34 Pbar).
• Vacuum Dry
– A vacuum is drawn in the chamber to the vacuum dry point.
• Dry
– Chamber continues to evacuate for 1 minute.
• Air Break
– Filtered air enters the chamber to relieve the vacuum within the
chamber.
• Retract Seal
– Steam is exhausted from the door seal.
• Complete
– The complete tone sounds and the cycle summary and end-
of-cycle messages are printed. Display returns to the main menu (screen
#1).
6. Once cycle is complete, the Dart Test cycle can be run. Refer to "Dart Test
Cycle Operation," next in this section.