POWR
TR
POWER TRAIN
PRIMARY SHEAVE AND DRIVE V-BELT
Order
Job/Part
Q’ty
Remarks
Primary sheave removal
Remove the parts in the order listed below.
Left side cover
Refer to “COWLINGS” in CHAPTER 3.
1
V-belt
1
2
Primary sheave assembly
1
For installation, reverse the removal
procedure.
1st
120 Nm (12 m•kg, 85 ft•lb)
2nd
60 Nm (6.0 m•kg, 43 ft•lb)
PRIMARY SHEAVE AND DRIVE V-BELT
37
Summary of Contents for RX10RTL
Page 2: ......
Page 8: ......
Page 21: ......
Page 25: ......
Page 29: ......
Page 141: ......
Page 259: ......
Page 265: ...SPEC 113 ...
Page 289: ...SPEC 113 ...
Page 313: ...SPEC 113 ...
Page 334: ...SPEC CABLE ROUTING CHEMINEMENT DES CABLES KABELDRAGNINGSSCHEMA CABLE ROUTING 134 ...
Page 336: ...SPEC CABLE ROUTING 136 ...
Page 338: ...SPEC CABLE ROUTING 138 ...
Page 340: ...SPEC CABLE ROUTING 140 ...
Page 342: ...SPEC CABLE ROUTING 142 ...
Page 344: ...SPEC CABLE ROUTING 144 ...
Page 346: ...SPEC CABLE ROUTING 146 ...
Page 348: ...SPEC CABLE ROUTING 148 ...
Page 350: ......
Page 351: ......
Page 352: ...2005 07 E F Sw ITP ...