![Vigilantplant TDLS8000 User Manual Download Page 214](http://html1.mh-extra.com/html/vigilantplant/tdls8000/tdls8000_user-manual_1022489214.webp)
<9. Inspection and Maintenance>
9-41
IM 11Y01D01-01EN
Time chart:
The valve operation during zero+span calibration execution and the timing when
the AO/DO output switches to Cal/Val mode are shown below. The following
figure shows an example for semi-automatic execution.
Operator
YH8000 screen
Valve1 Valve2
AO/DO
mode
[Screen operation] Start semi-automatic zero+span calibration
OFF
OFF Normal output
[Automatic valve operation] Purge with zero calibration gas
Zero calibration
gas purging
Span calibration
gas purging
ON
OFF
ON
ON
Cal/Val
(Zero calibration time elapses.)
(Span calibration time elapses.)
[Automatic valve operation] Discharge zero calibration gas
Span calibration
gas discharging
OFF OFF
(Span calibration stabilization wait time elapses.)
[Automatic valve operation] Purge with span calibration gas
Span calibration end
Normal output
Time
l
Offline validation 1+2
Piping:
Connect the piping as described in “Offline validation exclusive” in
section 9.4.1.
Configuration:
Configure the offline validation (see section 9.4.2) for validation 1 and 2.
Automatic execution configuration:
Configure from the following menu as necessary.
[HART] “Detailed setup>>Validation>>Offline validation 1+2”
[YH8000]
“
>>Configuration>>Validation>>Offline Validation 1 + 2”
Semi-automatic execution menu path:
[HART] “Diagnosis/Service>>Validation>>Semi-auto>>Semi-auto offline val 1+2”
[YH8000]
“
>>Execution>>Validation>>Semi-Auto>>Offline Validation 1 + 2”
Time chart:
The valve operation during offline validation 1+2 execution and the timing when
the AO/DO output switches to Cal/Val mode are shown below. The following
figure shows an example for semi-automatic execution.
Operator
HART/YH8000 screen Valve1 Valve2
AO/DO
mode
[Screen operation] Start semi-automatic offline validation 1+2
OFF
OFF Normal output
[Automatic valve operation] Check gas 1 purge
Check gas 1
purging
Check gas 2
purging
ON
OFF
ON
ON
Cal/Val
(Offline validation 1
validation time elapses.)
(Offline validation 2
validation time elapses.)
[Automatic valve operation] Check gas 2 discharge
Check gas 2
discharging
OFF OFF
(Offline validation 2
stabilization wait time elapses.)
[Automatic valve operation] Check gas 2 purge
Offline validation 1+2
Result display
Normal output
Time
3rd Edition: Jun. 10, 2016-00
Summary of Contents for TDLS8000
Page 10: ...ix IM 11Y01D01 01EN LT LV PL EST SLO H BG RO M CZ SK 3rd Edition Jun 10 2016 00...
Page 25: ...Blank Page...
Page 45: ...Blank Page...
Page 115: ...Blank Page...
Page 151: ...Blank Page...
Page 231: ...Blank Page...
Page 239: ...Blank Page...
Page 243: ...Blank Page...
Page 261: ...Blank Page...
Page 303: ......
Page 305: ......
Page 307: ......
Page 309: ......
Page 311: ......
Page 313: ...Blank Page...