Partitioning
208 SL8500: Systems Assurance Guide • July 2011
E24254-01
■
Tasks
Use
Table 95
to help prepare for partitioning.
Table 95. Steps and Tasks for Partitioning
✓
Step Task
Reference
Responsibility*
❏
1.
Team
Create a Team.
When planning for partitions, using a process similar to that of
the system assurance process, which is the exchange of
information among team members. Team members should
include representatives from both the customer and StorageTek
to ensure that all aspects of the process are planned carefully
and performed efficiently.
•
Customer
•
SE, PS
•
Svc Rep
❏
2.
Codes
Review the software and firmware
requirements. Update as required.
“Software and Firmware
Requirements” on
page 206
•
Customer
•
SE, PS
•
Svc Rep
❏
3.
Planning •
Create a planning team
•
Define the customer
expectations
•
Complete the assessment
•
Identify the configurations
•
Complete the planning diagrams
“Planning” on page 209
•
Customer
•
SE, PS
•
Svc Rep
❏
4.
Media
•
Verify the distribution of
cartridges and required tape
drives are available and ready.
•
Customer
❏
5.
Library
•
Convert a complex (if
necessary).
SL8500 Partitioning
Technical Brief
(PN 96269)
•
Svc Rep
❏
6.
License
•
License the partitioning feature
and create the library partitions.
•
Svc Rep
❏
7.
Hosts
•
Momentarily stop all host activity.
•
Make the hosts inaccessible.
•
Customer
❏
8.
Use
Instruct the customer how to:
•
Partition and re-partition
•
Override a CAP reservation
•
Customer
•
Svc Rep
•
SE = Systems engineer
•
PS = Professional services representative
•
Service = Service representative (Svc Rep)
•
Customer = System administrators, network administrators, system programmers, operators
Summary of Contents for StorageTek StreamLine SL8500
Page 4: ...Summary of Changes iv SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 12: ...Contents xii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 18: ...Tables xviii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 76: ...Introduction 56 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 97: ...E24254 01 Chapter 3 Site Survey Forms 77 Site Survey Forms Figure 21 Content Management Plan ...
Page 137: ...E24254 01 Chapter 4 Site Preparation 117 Site Preparation ...
Page 138: ...Site Preparation 118 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 198: ...Electrical Conversions 176 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 206: ...Comparisons 184 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 233: ...E24254 01 Appendix H Partitioning 211 Partitioning Make copies as necessary ...
Page 240: ...Partitioning 218 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 251: ...E24254 01 Appendix J Work Sheets 229 Work Sheets Figure 73 Content Management Work Sheet ...
Page 276: ...Index 254 SL8500 Systems Assurance Guide June 2011 E24254 01 ...
Page 277: ......
Page 278: ...Oracle Corporation Worldwide Headquarters 500 Oracle Parkway Redwood Shores CA 94065 U S A ...