E24254-01
Chapter 1 Introduction 15
Introduction
Connectors
When connecting the library to the main power circuits, if plugs and
connectors are required instead of using conduit,
Table 7
lists the Hubbell part
numbers (or equivalent) that can be used.
Circuit Breaker Ratings
The
minimum
circuit breaker ratings required for the service panel are:
Table 7. Hubbell Connectors and Plugs (IEC 309)
Part Number
Description
HBL330P6W
Single Phase US plug 30 amp
HBL330C6W
Single Phase US connector 30 amp
HBL332P6W
Single Phase Europe plug 32 amp
HBL332C6W
Single Phase Europe connector 32 amp
HBL532P6W
Wye plug 32 amp
HBL532C6W
Wye connector 32 amp
HBL460P9W
Delta plug 60 amp
HBL460C9W
Delta connector 60 amp
L15-50 R
NEMA Delta receptacle (250 V, 50 Amp) **
L15-50 P
NEMA Delta plug (250 V, 50 Amp) **
• Single phase minimum current requirement: 24 Amps-RMS
• Wye three phase minimum current requirement: 24 Amps-RMS
• Delta three phase minimum current requirement: 40 Amps-RMS
Table 8. Circuit Breaker Ratings
Type
Option
Panel Breaker
Service Rating
Connector
PDU Breaker
Conduit
(recommended)
Single Ph.
30 Amps
30 Amps
—
30 Amps
Delta
50 Amps
50 Amps
—
40 Amps
Wye
30 Amps
30 Amps
—
30 Amps
Connector
(US)
Single Ph.
30 Amps
30 Amps
30 Amps
30 Amps
Delta
50 Amps
50 Amps
50 A - NEMA**
60 A - IEC 309
40 Amps
Wye
30 Amps
30 Amps
30 Amps
30 Amps
Connector
(Europe)
Single Ph.
30 Amps
30 Amps
32 Amps
30 Amps
Delta
50 Amps
50 Amps
63 Amps
40 Amps
Wye
30 Amps
30 Amps
32 Amps
30 Amps
Note:
Wire size should be determined by the electrician.
Summary of Contents for StorageTek StreamLine SL8500
Page 4: ...Summary of Changes iv SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 12: ...Contents xii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 18: ...Tables xviii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 76: ...Introduction 56 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 97: ...E24254 01 Chapter 3 Site Survey Forms 77 Site Survey Forms Figure 21 Content Management Plan ...
Page 137: ...E24254 01 Chapter 4 Site Preparation 117 Site Preparation ...
Page 138: ...Site Preparation 118 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 198: ...Electrical Conversions 176 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 206: ...Comparisons 184 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 233: ...E24254 01 Appendix H Partitioning 211 Partitioning Make copies as necessary ...
Page 240: ...Partitioning 218 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 251: ...E24254 01 Appendix J Work Sheets 229 Work Sheets Figure 73 Content Management Work Sheet ...
Page 276: ...Index 254 SL8500 Systems Assurance Guide June 2011 E24254 01 ...
Page 277: ......
Page 278: ...Oracle Corporation Worldwide Headquarters 500 Oracle Parkway Redwood Shores CA 94065 U S A ...