E24254-01
Chapter 4 Site Preparation 105
Site Preparation
■
Preparing for the Installation
The SL8500 library requires extensive site preparation to accomplish an
error-free installation. Considerations that you and the customer must make
before the equipment arrives are outlined in the following sections.
Personnel
Warning: Weight of the upper modules:
You need to lift the upper drive bay and
robotic rail modules. These modules weigh approximately 40 kg (85
lb) and are raised a height of 1.7 m (5.5 ft).
The estimated time to physically install a library is about 24 person/hours.
This is based on
three qualified people
working approximately
eight hours
.
Note:
For initial planning, you may want to estimate it as two days to completely
install the library. This allows plenty of time to ensure a quality installation
and allow for training.
To make the best use of personnel, multiple tasks should be done
simultaneously. Time factors to consider include:
•
Guiding the pallets from the dock to the computer room
•
Removing packaging material when floor space is limited
•
Lifting requirements of 40 kg (85 lb) to attach upper frame assemblies
•
Configuring the library and up to 64 drives with switches and cables
Installation tips for these situations are supplied in the
Installation Manual
.
Power
Keep in mind the following power considerations:
1. A
qualified electrician
is required to install the power cable and must:
•
Use flexible or rigid conduit
•
Adhere to the torque specifications;
2 Nm (18 in-lb) torque
•
Attach a 90-degree elbow-down fitting to the library’s PDU or there will be
problems attaching the cover and closing the rear door
Make sure time has been scheduled and coordinated with the electrician.
2. Remember that there are two power configurations and four branch circuit
options from which the customer can choose.
Make sure
the correct configuration and branch circuit is selected.
3. Plan the location for the second set of power wiring even if the customer is
not purchasing the redundant power feature.
Make sure each power source is on a separate branch circuit; otherwise the
redundant power feature is defeated (for 2N power configurations).
Summary of Contents for StorageTek StreamLine SL8500
Page 4: ...Summary of Changes iv SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 12: ...Contents xii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 18: ...Tables xviii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 76: ...Introduction 56 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 97: ...E24254 01 Chapter 3 Site Survey Forms 77 Site Survey Forms Figure 21 Content Management Plan ...
Page 137: ...E24254 01 Chapter 4 Site Preparation 117 Site Preparation ...
Page 138: ...Site Preparation 118 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 198: ...Electrical Conversions 176 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 206: ...Comparisons 184 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 233: ...E24254 01 Appendix H Partitioning 211 Partitioning Make copies as necessary ...
Page 240: ...Partitioning 218 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 251: ...E24254 01 Appendix J Work Sheets 229 Work Sheets Figure 73 Content Management Work Sheet ...
Page 276: ...Index 254 SL8500 Systems Assurance Guide June 2011 E24254 01 ...
Page 277: ......
Page 278: ...Oracle Corporation Worldwide Headquarters 500 Oracle Parkway Redwood Shores CA 94065 U S A ...