Site Preparation
106 SL8500: Systems Assurance Guide • July 2011
E24254-01
Floor
Several requirements exist for the customer’s
floor
:
Raised Floor
The SL8500 library does not require a raised floor. The primary concern is that
the environmental requirements are met. As long as there is adequate airflow
and environmental specifications are met, a raised floor is not required.
Weight
The weight of the library can vary depending on the configuration and number
of modules (see
Table 39 on page 84
for the listed weights). Make sure the
customer’s floor has been checked to verify that it will support this weight.
Co-planar
It is recommended that the customer’s floor be laser-leveled before receiving
any equipment and that the library modules be situated along the same
horizontal plane (co-planar
1
) to within ± 25 mm (1 in.) tolerance.
Co-planer positioning of the library modules is extremely important, because
up to six modules may be joined together linearly. If you are not within a
25 mm (1 in.) height condition between the first and second module, this will
result in a 152 mm (6 in.) condition at the last module. Out-of-plane conditions
will cause binding, premature wear, and damage to the HandBots.
Construction Area
The minimum working area (not including the space required for the pallets) is
approximately 56 m
2
(600 ft
2
).
■
Installation Tools
Table 49
lists the tools available in the installation kit that may be ordered
through Logistics if one is
not
available locally.
Notes:
•
These tools are
not
supplied with each library.
•
You should always order the kit instead of ordering the tools separately.
•
Separate tool orders are
only
for replacing damaged or missing tools.
•
Once used, retain the kit for re-use locally or ship within your region.
•
Kit dimensions are: 99 cm (39 in.) long, 71 cm (28 in.) wide, and 51 cm
(20 in.) high. The kit comes with an extendable handle and wheels.
•
Make sure you order any
additional items
(see the following page)
1.
Lying or acting in the same plane.
Summary of Contents for StorageTek StreamLine SL8500
Page 4: ...Summary of Changes iv SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 12: ...Contents xii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 18: ...Tables xviii SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 76: ...Introduction 56 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 97: ...E24254 01 Chapter 3 Site Survey Forms 77 Site Survey Forms Figure 21 Content Management Plan ...
Page 137: ...E24254 01 Chapter 4 Site Preparation 117 Site Preparation ...
Page 138: ...Site Preparation 118 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 198: ...Electrical Conversions 176 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 206: ...Comparisons 184 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 233: ...E24254 01 Appendix H Partitioning 211 Partitioning Make copies as necessary ...
Page 240: ...Partitioning 218 SL8500 Systems Assurance Guide July 2011 E24254 01 ...
Page 251: ...E24254 01 Appendix J Work Sheets 229 Work Sheets Figure 73 Content Management Work Sheet ...
Page 276: ...Index 254 SL8500 Systems Assurance Guide June 2011 E24254 01 ...
Page 277: ......
Page 278: ...Oracle Corporation Worldwide Headquarters 500 Oracle Parkway Redwood Shores CA 94065 U S A ...