System Options:
Cooling Stage / Waterless Cooling Stage
9-24
FIGURE 9-22
OUTER AND INNER CABLES
Water Chiller, Flow Box and Cooling Water Hoses
Note:
In case the waterless Cooling stage is installed the following devices
are not available.
An external water chiller is provided to efficiently remove excess heat
from the temperature stage.
FIGURE 9-23
THE WATER FLOW BOX CONTROL BOARD
The water flow box is installed between the water chiller and the
chamber feed-through plate. It monitors a water flow via a sensor on
each line and closes both solenoid valves if a failure is detected to
protect the system against a water leak into the chamber.
Cooling water hoses
are delivered: the shortest set of hoses is
connected to the stage on one end, the other end goes to the inside of
the feed-through plate. One set of hoses goes from the outside of the
chamber feed-through plate to the water flow box. Next one connects
the water chiller with the water flow box.
COOLING STAGE INSTALLATION
The chamber feed-through plate should be in place and remain
installed.
1.
Vent the specimen chamber and open the door.
2.
Remove any sample holder from the stage rotation head.
Summary of Contents for Quanta FEG 250
Page 8: ...C vi...
Page 28: ...System Operation Quanta FEG System States 3 10...
Page 108: ...Alignments 1 Gun Alignment 6 6...
Page 114: ...Alignments 154 Water Bottle Venting 6 12 154 Water Bottle Venting...
Page 152: ...System Options Automatic Aperture System 9 4...
Page 154: ...System Options Nav Cam 9 6 401 NAV CAM AUTOBRIGHTNESS...
Page 177: ...System Options Cooling Stage Waterless Cooling Stage 9 29...