72
BU 0600 en-3221
4.2.3 Motor control commissioning steps
The main commissioning steps are mentioned below in their ideal order. Correct assignment of the
inverter / motor and the mains voltage is assumed. Detailed information, especially for optimisation of
the current, speed and position control of asynchronous motors is described in the guide "Control
optimisation" (AG 0100). Detailed commissioning and optimisation information for PMSM in CFC
closed loop mode can be found in the "Drive optimisation" guide (AG 0101). Please contact our
Technical Support.
1.
Carry out the motor connection as usual (note ∆ / Y!). Connect the enco
der, if present
2. Connect the mains supply
3. Carry out the factory setting (P523)
4. Select the basic motor from the motor list (P200) (ASM types are at the beginning of the list, PMSM
types are at the end, designated by their type (e.g.
…80T…
))
5. Check the motor data (P201 … P209) and compare with the type plate / motor data sheet
6. Measure the stator resistance (P220)
P208, P241[-01] are measured, P241[-02] is calculated
(Note: is an SPMSM is used, P241[-02] must be overwritten with the value from P241[-01])
7. Encoders: Check the settings (P301, P735)
8. with PMSM only:
a. EMF voltage (P240)
motor type plate / motor data sheet
b. Determine / set reluctance angle (P243) (not required with NORD motors)
c. Peak current (P244)
motor data sheet
d. Only for PMSMs in VFC mode:
determine (P245), (P247)
e. Determine (P246)
9. Select the operating mode (P300)
10. Determine / adjust the current control (P312 – P316)
11. Determine / adjust the speed control P310, P311)
12. PMSM only:
a. Select the control method (P330)
b. Make the settings for the starting behaviour (P331 … P333)
c. Make the settings for the 0 pulse of the encoder P334 … P335)
d.
Activation of slip error monitoring (P327 ≠ 0)
Information
Further information for commissioning NORD IE4 - motors with NORD frequency inverters can be
found in the technical information
Information
HTL encoder length limit
The length of the HTL encoder cable should not exceed 10 m.
Содержание SK 510P
Страница 1: ...BU 0600 en NORDAC PRO SK 500P Manual with installation instructions...
Страница 4: ...NORDAC PRO SK 500P Manual with installation instructions 4 BU 0600 en 3221...
Страница 223: ...7 Technical data BU 0600 en 3221 223...
Страница 233: ...8 Additional information BU 0600 en 3221 233 8 3 4 EU Declaration of Conformity...
Страница 253: ...Key word index BU 0600 en 3221 253...
Страница 254: ...NORDAC PRO SK 500P Manual with installation instructions 254 BU 0600 en 3221...
Страница 255: ...Key word index BU 0600 en 3221 255...
Страница 256: ...6076002 3221...