Chapter 5 Trial Operation and Tuning
ASDA-B2
5-6
Revision May, 2018
(7) When the screen displays:
Warning of under voltage:
Corrective actions:
Check if the wiring of main circuit input voltage is correct.
Use voltmeter to measure if the main circuit voltage is normal.
Use voltmeter to measure if the power system complies with the specification.
Note: During the process of power on or servo on, if an alarm occurs or shows any
abnormal display, please contact the distributors.