Chapter 10 Commissioning the Shelves
Installation and Commissioning Manual
323
F
S
P
3000R
7 R
11
.1 8000
0015930
Issue
B
, ©
2012
ADVA AG Optical Netw
orking
ADVA Conf
idential
Commissioning the NE
This section provides a brief overview of the commissioning process. It is suffi-
cient to allow you to access the NE remotely and then complete the whole com-
missioning later.
Refer to the
Provisioning and Operations Manual, Chapter 2
for details on com-
pleting the commissioning process.
Procedure
Step 1
Use the installation plan to identify the master shelf.
Step 2
Set the shelf IDs as described in
.
Step 3
Connect to the NE as described in
“Connecting to the Network Ele-
.
Step 4
Start a terminal emulation program, see
Step 5
Log into the NE using the user account
ADMIN
with a valid
ADMIN password
or the default password
“CHGME.1”
. Refer also
“Logging On to the Network Element” on p. 350
.
The password is not case sensitive. ADVA Optical Networking recom-
mends changing all passwords as soon as possible.
Step 6
To configure basic parameters, do as follows:
a) Read the installation plan and find the IP address, subnet mask
and default gateway that are specified for this network element
(NE).
b) Enter these parameters as described in
.
c) Configure SNMP settings, see the
Provisioning and Operations
Manual
for details.
d) Configure the date and time, see
.
Step 7
Configure access via the serial port, see
.
Step 8
Configure the Ethernet access to be able to reach the NE remotely.
Refer to
“Ethernet Port Settings” on p. 362
Step 9
Assign all shelves in the NE to the database maintained on the NE as
described in the
Provisioning and Operations Manual
.
Step 10 If an eROADM is installed, commission the eROADM, see
3000R7 ROADM-C40/40/OPM-3HU/2DC Commissioning
End of Procedure