Breaker Monitor and Metering Functions
8-13
SEL-311L Instruction Manual
Via Front Panel
The information and reset functions available via the previously discussed serial port commands
BRE
and
BRE R
are also available via the front-panel OTHER pushbutton. See Figure 11.3 in
Section 11: Front-Panel Interface
.
Determination of Relay-Initiated Trips and Externally Initiated Trips
See
BRE Command (Breaker Monitor Data)
in
Section 10: Line Current Differential
Communications and Serial Port Communications and Commands
. Note in the
BRE
command response that the accumulated number of trips and accumulated interrupted current are
separated into two groups of data: that generated by relay-initiated trips (Rly Trips) and that
generated by externally initiated trips (Ext Trips). The categorization of this data is determined
by the status of the TRIP Relay Word bit when the SEL
OGIC
control equation breaker monitor
initiation setting BKMON operates.
Refer to Figure 8.3 and the accompanying explanation. If BKMON newly asserts (logical 0 to
logical 1 transition), the relay reads in the current values (Phases A, B, and C). Now the decision
has to be made: where is this current and trip count information accumulated? Under
relay-initiated trips or externally initiated trips?
To make this determination, the status of the TRIP Relay Word bit is checked at the instant
BKMON newly asserts (TRIP is the logic output of Figure 5.4). If TRIP is asserted (TRIP =
logical 1), the current and trip count information is accumulated under relay-initiated trips (Rly
Trips). If TRIP is deasserted (TRIP = logical 0), the current and trip count information is
accumulated under externally initiated trips (Ext Trips).
Regardless of whether the current and trip count information is accumulated under relay-initiated
trips or externally initiated trips, this same information is routed to the breaker maintenance
curve for continued breaker wear integration (see Figure 8.3 through Figure 8.7).
Setting Example
As discussed previously, the SEL
OGIC
control equation breaker monitor initiation may be set:
BKMON = TRIP + TRIP87
Thus, any new assertion of BKMON will be deemed a relay trip, and the current and trip count
information is accumulated under relay-initiated trips (Rly Trips).
Additional Example
Refer to Figure 8.8. Output contact OUT101 is set to provide tripping:
OUT201 = TRIP + TRIP87
Note that optoisolated input IN106 monitors the trip bus. If the trip bus is energized by output
contact OUT201, an external control switch, or some other external trip, then IN106 is asserted.
Summary of Contents for SEL-311L
Page 6: ......
Page 8: ......
Page 26: ......
Page 54: ......
Page 144: ......
Page 216: ......
Page 252: ......
Page 302: ......
Page 338: ......
Page 480: ......
Page 484: ......
Page 486: ......
Page 502: ......
Page 532: ...12 28 Standard Event Reports and SER Date Code 20010625 SEL 311L Instruction Manual 4 ...
Page 552: ......
Page 554: ......
Page 574: ......
Page 576: ......
Page 596: ......
Page 602: ......
Page 628: ......
Page 656: ......
Page 662: ......
Page 664: ......
Page 688: ......
Page 700: ......
Page 716: ......
Page 722: ......
Page 734: ......