15 - 11 15 - 11
15 TROUBLESHOOTING
Description of problem
Check item
Check contents
Check procedure
Corrective action
Check if the SD LED and RD
LED are flashing at the faulty
station.
Connect the cable properly.
A2-5 Cables
Is there any disconnection, short-
circuit, incorrect wiring, faulty
connection, or status out of
specifications (transmission
distance, distance between
stations, transmission cable,
coexistence of different cables or
FG connection)?
Check the cable of the closest
faulty station from the master
station, when multiple stations are
sequentially faulty to the terminal
of the transmission path. (multiple
stations)
Connect the cable properly.
Is the power on at the faulty
station?
Turn the power supply on.
A2-6
Power supply (for
communication)
Is the power off or out of the
range of use?
Is the supplied power within the
specified range?
Set the supplied voltage to within
the specified range.
Check if the transmission cable
and power wiring are separated
enough.
Wire the transmission cable and
power wiring as separated as
possible. (recommended to keep
a distance of more than 100mm)
Check if the FG is separated from
the power system GND.
Set FG and the power system
GND apart.
A2-7 Noise
Is there any noise on the
transmission cable?
Reduce the transmission speed
and then check the occurrence
frequency.
Take measures against noise.
Reduce the transmission speed.
A2-9
Slave station failure
Is the slave station failed?
Replace the failed station and
check the operation.
Fix or replace the failed slave
station.
Some station(s)
cannot be linked.
A2-10
Standby master
station
Is the standby master station
controlling the data link?
Check if the master station
switching status is in the standby
master station, with the master
station CC-Link diagnostics.
Reboot the system and set the
control by the master station.
A3-1 Cables
Is there any cable/connector
disconnected or out of
specifications?
Check the cable between the
master station and slave station.
Connect the corresponding cable
properly.
A3-2 Parameter
setting
Is not the sequence scan too
long? (synchronous mode)
Does the sequence scan time
exceed the tolerance?
10 Mbps : 50 ms
5 Mbps : 50 ms
2.5 Mbps: 100 ms
625 kbps: 400 ms
156 kbps: 800 ms
Switch to the asynchronous
mode, or reduce the transmission
speed.
A3-3
Power supply (for
communication)
Is the power off or out of the
range of use?
Check the power supply of the
master station and all slave
stations.
Set the supplied voltage to within
the specified range.
Check if the transmission cable
and power wiring are separated
enough.
Wire the transmission cable and
power wiring as separated as
possible. (recommended to keep
a distance of more than 100mm)
Check if the FG is separated from
the power system GND.
Set FG and the power system
GND apart.
A3-4 Noise
Is there any noise on the
transmission cable?
Reduce the transmission speed
and then check the occurrence
frequency.
Take measures against noise.
Reduce the transmission speed.
A3-5
Master station failure Is the master station failed?
Check if the system operates
properly after replacing the
master station.
Fix or replace the master station.
Unable to link the
entire system
occasionally.
A3-6 Link
stop
Is the data link stop instruction
being executed properly?
Check if the data link stop
(SB0002) is turned on.
Disable the data link stop
(SB0002).
Do not use devices which read
SB002 simultaneously.
(To the next page)
Summary of Contents for L26CPU-BT
Page 1: ......
Page 2: ......
Page 32: ...3 5 3 5 3 SPECIFICATIONS ...
Page 51: ...4 2 4 2 4 PROCEDURE BEFORE OPERATION 4 ...
Page 61: ...6 4 6 4 6 INSTALLATION AND CONNECTION ...
Page 63: ...6 6 6 6 6 INSTALLATION AND CONNECTION 8 The connection method is shown below ...
Page 70: ...6 13 6 13 6 INSTALLATION AND CONNECTION ...
Page 72: ...6 15 6 15 6 INSTALLATION AND CONNECTION ...
Page 139: ...8 33 8 33 8 FUNCTIONS ...
Page 151: ...8 45 8 45 8 FUNCTIONS ...
Page 246: ...11 9 11 9 11 EXAMPLE OF COMMUNICATION BETWEEN THE MASTER STATION AND REMOTE DEVICE STATIONS ...
Page 311: ...13 2 13 2 13 COMMUNICATION BETWEEN THE MASTER STATION AND INTELLIGENT DEVICE STATIONS MEMO 13 ...
Page 321: ...14 10 14 10 14 EXAMPLE OF COMMUNICATION WHEN MOUNTING MODULES ON THE HEAD MODULE ...
Page 326: ...15 5 15 5 15 TROUBLESHOOTING To the next page ...
Page 327: ...15 6 15 6 15 TROUBLESHOOTING To the next page ...
Page 328: ...15 7 15 7 15 TROUBLESHOOTING ...
Page 329: ...15 8 15 8 15 TROUBLESHOOTING 2 Troubleshooting by status logging ...
Page 436: ...App 72 App 72 APPENDIXES 7 Operating procedure of the transmission speed test ...
Page 439: ...App 75 App 75 APPENDIXES MEMO ...
Page 447: ......
Page 448: ......
Page 449: ......