19. For safe operation
WARNING
- 191 -
Fo
r s
afe
op
er
atio
n
19-2-4 Boom derricking and lowering
(0099-0016-3E)
(1)
When you derrick and lower the boom, the working radius
increases as the angle of the boom decreases, increasing the risk
of tip over.
(2) Beware of overhoisting the hook
When the boom is lowered or extended, the hook is wound up,
possibly causing overhoisting and damage when the hook block
hits the boom top. Normally the overhoisting detector will act to
prevent this, but if the detector is inoperative and overhoisting
occurs, lower the hook to the proper position.
When a lifting load is overhoisted, the distance between the
load and the boom is reduced and the load can hit the boom and
damage it.
The size of the lifting load must also be taken into account.
19-2-5 Winch operation
(0099-0017-2E)
(1) Choose a hook and wire rope number of parts of line suitable
for the mass of the load from the lifting capacity chart.
(2)
When lifting the load, pause briefly when it has just left the
ground to check for safety and then continue the operation.
Summary of Contents for PREMIUM CITYRANGE CR-200RF
Page 2: ...218711 背厚 14 5 mm 中 ...
Page 14: ... 12 4 Dimensions T217591 021 0E Specification of CR 200Rf ...
Page 16: ... 14 MEMO ...
Page 24: ... 22 MEMO ...
Page 30: ... 4 MEMO ...
Page 36: ... 10 MEMO ...
Page 38: ... 12 3 General operation devices 2 Outside the cab ...
Page 60: ... 34 MEMO ...
Page 74: ... 48 MEMO ...
Page 82: ... 56 7 Air conditioner 7 6 Display when errors are detected T217921 020 0E ...
Page 120: ... 94 MEMO ...
Page 129: ... 102 MEMO ...
Page 138: ... 111 17 Drive operation devices Drive operation devices ...
Page 139: ... 112 17 Drive operation devices ...
Page 153: ... 126 17 Drive operation devices ...
Page 154: ... 127 17 Drive operation devices Drive operation devices ...
Page 237: ... 208 21 Crane operation devices 21 Crane operation devices 061A 0005 0E 1 Inside the cab ...
Page 238: ... 209 21 Crane operation devices Crane operation devices ...
Page 239: ... 210 21 Crane operation devices 2 Outside the cab ...
Page 259: ... 230 22 Crane operation when the outriggers are used ON OFF ...
Page 299: ... 270 24 Crane operation NOTE Extension retraction sequence for each boom length ...
Page 320: ...26 Preoperational checks Pre drive checks 290 ...
Page 321: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 291 ...
Page 322: ...26 Preoperational checks Pre drive checks 292 ...
Page 329: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 299 ...
Page 330: ...26 Preoperational checks Pre drive checks 300 ...
Page 331: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 301 ...
Page 332: ... 302 MEMO ...
Page 340: ... 310 MEMO ...
Page 342: ...899 92187110 ...