NO TICE
Place only one server node in an ESD bag.
Step 7 Install filler modules.
NO TICE
Install filler panels in vacant slots. Otherwise, the ventilation, heat dissipation,
electromagnetic shielding, and dustproof effects of the chassis will be affected.
----End
8.3.4 Installing an XH321 V5
Procedure
Step 1 Determine the position of the server node in the chassis.
Figure 8-7 Positions and slot numbers of the XH321 V5 server nodes
NO TE
Install the lower server nodes and then the upper server nodes.
Step 2 Remove filler modules.
NO TE
Perform this operation only when filler modules are installed.
1. Press the ejector release button on the filler module. See (1) in
2. Fully open the ejector lever. See (2) in
3. Holding the ejector lever, pull the filler module from the chassis. See (3) in
.
FusionServer Pro XH321 V5 Server Node
Maintenance and Service Guide
8 Parts Replacement