P9 ASD Installation and Operation Manual
Installation Precautions
Location and Ambient Requirements
•
The TIC ASD is intended for permanent installations only.
•
Installation should conform to the
National Electrical Code — Article 110
(NEC) (
Requirements
For Electrical Installations
), all regulations of the
Occupational Safety and Health
Administration
, and any other applicable national, regional, or industry codes and standards.
Note:
For ALL references to the National Electrical Code (NEC), see the latest release of
the National Electrical Code.
•
Select a mounting location that is easily accessible, has adequate personnel working space, and
adequate illumination for adjustment, inspection, and maintenance of the equipment (refer to the
NEC Article 110-13).
•
DO NOT
mount the ASD in a location that would produce catastrophic results if it were to become
dislodged from its mounting location (equipment damage or injury).
•
DO NOT
mount the ASD in a location that would allow it to be exposed to flammable chemicals or
gases, water, solvents, or other fluids.
•
Avoid installation in areas where vibration, heat, humidity, dust, fibers, metal particles, explosive/
corrosive mists or gases, or sources of electrical noise are present.
•
The installation location shall not be exposed to direct sunlight.
•
Allow proper clearance spaces for installation.
DO NOT
obstruct the ventilation openings. Refer to
the section titled
Installation and Connections on pg. 14
for further information on ventilation
requirements.
•
The ambient operating temperature range of the P9 ASD is 14° to 104° F (-10° to 40° C).
Mounting Requirements
•
Only
Qualified Personnel
should install this equipment.
•
Install the unit in a secure and upright position in a well-ventilated area.
•
As a minimum, the installation of the equipment should conform to the
NEC — Article 110
(NEC), OSHA, as well as any other applicable national, regional, or industry codes and standards.
•
Installation practices should conform to the latest revision of NFPA 70E Electrical Safety
Requirements for Employee Workplaces.
•
It is the responsibility of the ASD installer/maintenance personnel to ensure that the unit is installed
into an enclosure that will protect personnel against electric shock.
Содержание P9
Страница 1: ...TM P9 ASD Install Op Manual TOSHIBA P9 ASD INSTALLATION OPERATION MANUAL DN 64054 004 February 2013 ...
Страница 2: ......
Страница 3: ...Document Number 64054 004 February 2013 P9 ASD Installation Operation Manual TM ...
Страница 4: ......
Страница 280: ...270 P9 ASD Installation and Operation Manual Figure 38 See Tables 17 and 18 for Actual Dimensions ...
Страница 281: ...P9 ASD Installation and Operation Manual 271 Figure 39 See Tables 17 and 18 for Actual Dimensions ...
Страница 282: ...272 P9 ASD Installation and Operation Manual Figure 40 See Tables 17 and 18 for Actual Dimensions ...
Страница 285: ...P9 ASD Installation and Operation Manual 275 Figure 43 See Table 18 for the associated device Dimensions are in in cm ...
Страница 304: ...294 P9 ASD Installation and Operation Manual W W T3 16 Warranty Card 2 W Phase Over Current 265 ...
Страница 305: ......