iManager NetEco 6000
Device Installation and Commissioning Guide
3 Installing Devices
Issue 03 (2019-03-10)
Copyright © Huawei Technologies Co., Ltd.
19
Figure 3-7
Installing the power modules for a 24-port LAN switch
3.4 Installing an ECC500/ECC800 Collector
Procedure
Step 1
Determine the mounting holes for the ECC collector in the network cabinet based on the
engineering layout diagram, adjust the guide rails or trays, and install floating nuts.
Step 2
Gently put the ECC collector into the network cabinet.
Step 3
Secure the ECC collector in the network cabinet by clockwise tightening the M6 screws on
the left and right mounting ears.
Figure 3-8
Installing an ECC collector
Step 4
Connect the ECC collector power cable to the PDU2000.