iManager NetEco 6000
Device Installation and Commissioning Guide
2 Installation Preparations
Issue 03 (2019-03-10)
Copyright © Huawei Technologies Co., Ltd.
9
Huawei will not be liable for any consequence caused by the violation of this document.
The requirements are as follows:
Customers' installation personnel must be trained by Huawei and understand how to
install and operate a Smart Module.
The number of installation personnel varies depending on the project progress and the
installation environment. Typically, three to five persons are required.
2.3 Tools and Instruments
This section lists the tools and instruments required for installation.
Table 2-1
Common tools
Tool Name, Specifications, and Appearance
Protective gloves
Marker
Measuring tape (5
m)
Level
Step ladder (2 m)
Phillips screwdriver
Phase sequence
meter
Flat-head
screwdriver (2–5
mm)
Adjustable wrench
(6")
Socket wrench
M4/M6/M8/M12
Hex key
Box-end wrench
M6/M8/M12
Torque wrench (28
mm)
Solid wrench
(12#/13#/18#)
Cotton cloth
Label