iManager NetEco 6000
Device Installation and Commissioning Guide
6 Adding Devices
Issue 03 (2019-03-10)
Copyright © Huawei Technologies Co., Ltd.
221
Figure 6-75
Configuring parameters for a hydrogen detector MODBUS-RTU
Table 6-33
MODBUS-RTU device parameter description
Parameter
Description
Name
Device name
IP address
Set the IP address of the data collector to which the device connects.
Port
Set this parameter to the port through which the device connects to
the collector.
To learn ports on the ECC collector, see Setting RS485 Parameters
for the ECC500 V6 Collector.
Device Address
Set this parameter to the address set on the device.
Timeout period
Timeout duration for connection test (set to
3s
by default)
Step 7
Click
Connection Test
to start the connection test.
Step 8
After the connection test is successful, click
in the toolbar to save the device
information.