Planned maintenance
These instructions include procedures for planned maintenance (PM) for the B30. The Planned
maintenance should be performed once a year.
These instructions include “
Planned maintenance check form, B30
”, which to be filled in when
performing the corresponding procedures.
4.1 Visual inspection/preparation
4.1.1 Before beginning
NOTE: Wear a static control wrist strap when handling PC boards. Electrostatic discharge may
damage components on the board.
•
Make sure that the monitor is turned off.
•
Disconnect the mains power cord.
•
If the monitor is connected to the network, disconnect the CAT-5 cable from the monitor.
4.1.2 General
1.
Check all the units visually. Check that all parts are intact and that the cables and screws
are connected and tightened properly. Check the connector pins are intact
2.
Check that the modules go in smoothly and lock up properly.
3.
Replace the batteries, if necessary.
The manufacturer recommendations are:
−
Replace the SRAM/Timekeeper battery on the CPU board every 8 years.
NOTE: The Factory Reset must be performed if the SRAM/Timekeeper battery is replaced.
4.
Check that the fuses are of the correct rating.
5.
Check the ventilation holes of the monitor and clean of dust if necessary.
6.
Check the battery status from
Battery setup
menu: If “failed”, renew the battery. If
“condition”, perform the condition cycle.
"
NOTE: Batteries are recommended to be conditioned every six months.
NOTE: Check that tubes are not contaminated. Any contamination inside the tubing can
increase a risk of faulty operation in valves or sensors. If any contamination inside the tubing is
noticed then it is recommended to send the module to factory repair.
4.1.3 E-PSM(P)W Module
1.
Check the NIBP pump filter. Replace the filter, if necessary.
Plug the module back into the frame.
2.
Check internal parts:
−
screws are tightened properly
−
connectors are connected properly
−
NIBP tubing is attached properly
−
there are no loose objects inside the module
Summary of Contents for b30
Page 2: ......
Page 12: ...B30 Patient Monitor 8 Document no 2044677 001...
Page 13: ...1 Introduction...
Page 14: ......
Page 61: ...2 Installation...
Page 69: ...3 Maintenance...
Page 70: ......
Page 105: ...4 Troubleshooting...
Page 106: ......
Page 125: ...5 Service Menu...
Page 126: ......
Page 158: ...B30 Patient Monitor 5 32 Document no 2044677 001...
Page 159: ...6 Field replaceable unit...
Page 160: ......
Page 166: ...B30 Patient Monitor 6 6 Document no 2044677 001 1 6 Frame for B30 Frame for B30...
Page 183: ...Frame disassembly 6 23 Document no 2044677 001...
Page 190: ...B30 Patient Monitor 6 30 Document no 2044677 001...
Page 191: ...7 Technical specification...
Page 192: ......
Page 198: ...B30 Patient Monitor 7 6 Document no 2044677 001...
Page 199: ...8 N F C REC Module...
Page 200: ......
Page 238: ...B30 Patient Monitor A 6 Document no 2044677 001...
Page 251: ......