Chapter 6: System commissioning
ZP3 Fire Control Panel Installation, Commissioning, and Maintenance Manual
107
• Check that the installation of the wiring complies with the requirements of
Appendix A “ZP wiring guide” on page 117 and that it has been sized
correctly. Particularly check that all Z-loops are screened, and that the
screens are continuous, and earthed at the panel.
• Make sure there are no sections of floating screens. Also verify that proper
separation has been maintained from high-voltage mains cabling.
• Check that data cabling (RS-232 and RS-485) is screened, continuous, and
earthed, and separated from mains and Z-loop wiring.
Make sure that the plastic protective tab installed between the metal securing clip
and the lithium clock batteries on the main board is removed to enable the clock
(see Figure 54 below).
¤
¥
¦
§
¨
©
«
ª
¬
´
®
»
ú
Õ
³
µ
µ
©
¨
Å
¶
¨
®
µ
©
»
µ
¥
Þ
©
µ
³
Õ
Plastic protective tab
The software configuration can be verified by checking the system configuration
printout from the Planner programme. If the system was not programmed using
Planner, then a printout of the zoning and I/O-mapping functions can be obtained
from the panel. The following must be checked and verified:
• Access control levels are correctly set
• System configuration (global settings) have been set in the Setup menu
• AGV function has been enabled if this feature is required
• Panel number is correctly set
• Panel has been defined as a stand-alone or ZP-NET panel
Содержание ZP3
Страница 76: ...Chapter 3 Field wiring 68 ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual...
Страница 112: ...Chapter 5 System configuration 104 ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual...
Страница 162: ...Appendix B ZP3 system maintenance 154 ZP3 Fire Control Panel Installation Commissioning and Maintenance Manual...
Страница 163: ......