7 Commissioning
Checking procedure before the test run
SMGB0091 rev.2 - 11/2015
119
7
• Check to ensure the operating temperature:
-
Cooling operation:
Indoor DB 21.5ºC and above,
Indoor WB 16ºC and above,
Outdoor DB 0ºC and above
-
Heating operation:
Indoor DB 27ºC and below.
(*) About insulation resistance
The insulation might be reduced during a test run or after being left with the main power OFF for a long time, due to
refrigerant accumulation in the compressor. Check the following when the insulation resistance lowers to 1 MΩ or below,
or in case that the ground-fault circuit interrupter activates:
1
Remove compressor cables and measure the insulation resistance of the compressor alone. If the resistance is over
1 MΩ, other insulation failure of electric live part may exist.
2
If the resistance is under 1 MΩ, remove compressor cables from the inverter PCB and turn the power ON and
energize the oil heater. Measure the resistance after more than three hours of electric current application. If the
insulation resistance recovers, the compressor does not have problems. In case that the resistance does not recover,
compressor failure may exist. (More time may be required to apply the current depending on the conditions of air,
pipe length or the refrigerant).
?
N O T E
To reconnect the removed compressor cables, re-caulk the terminal using a tool like long nose pliers in order that the Faston terminal
does not remain loose.
In case of Earth Leakage Breaker (ELB) activation, please confirm the rated capacity of ELB as well. Earth leakage
breaker (ELB) shall be inverter compatible, and select a high-sensitive and high-speed model for sensed current
rating under 30 mA (activation time within 0.1 sec).