TopClean S CPC 30
6 Commissioning
Hauser
73
Required settings according to the example (bold: to be set by user):
In this way, each day can be programmed (or copied) individually.
Field OAA1
Field OAA2
(with "Clean")
Field OAA2
(with "Clean Int")
Clean
01 Water
60 s
01 Water
60 s
11:00
11:02
02 +Cleaner
60 s
02 +Cleaner
60 s
Clean
03 Water
0 s
03 Water
0 s
18:00
18:02
04 Rep. Clean.
0x
Measuring time
1800 s
Clean Int
18:20
24:00
CODE
CHOICE
(default = bold)
INFO
(E1, 2 = Editor types, s. page 28)
User
settings
O1
Weekly progr.
Clean trigger
Ext. Control
off
off
off
Select control levels
Select the function which will trigger Chemoclean
cleaning.
E2
O2
Weekly progr.
Clean trigger
Ext. Control
off
off
off
Note in display:
Displays the current system status
–
O3
Weekly progr.
User prog.
Select the configuration menu
Weekly programme
: Select only with "weekly
programme on"
User programme
: Here you can create customer-
specific programmes using the Programme Editor (see
Programme Editor, p. 68).
E1
Weekly programme:
OA1
Monday
Tuesday
.....
Sunday
1
2
...
0
Select weekday menu
Select cleaning day. The number of cleaning triggers
for the day is shown after each day.
E1
OA2
Edit day?
Copy day?
Select day function
Edit day
: You edit the cleaning sequence for this day.
Copy day
: The day selected in OA1 is copied to the
day selected in the field below.
E1
Edit day:
OAA1
Clean
18:22 18:23
No progr.
View/edit day programme
You can see the complete daily programme or "No
Progr.". You can overwrite the option and also the
already set programmes by making a new selection.
The start and finish times are always given.
Example:
Clean
18:22 (start time) 18:23 (finish time)
User prog.: Use of a programme you created, (see
Programme Editor, p. 68)
E1
Содержание TopClean S CPC 30
Страница 127: ...TopClean S CPC 30 11 Appendix Endress Hauser 127...
Страница 138: ...11 Appendix TopClean S CPC 30 138 Endress Hauser...
Страница 144: ...12 Index TopClean S CPC 30 144 Endress Hauser...