12713020-002-2 Revision D – April 2004
SSU-2000 User’s Guide 103
Chapter 4 Commissioning
The commissioning tests for the SSU-2000 are checklist-based operational tests
that field engineers perform at the installation site after completion of installation,
system turn-up, and provisioning to verify that the system is correctly installed,
configured and operating properly. At this point, the system is ready to be placed in
service.
Record the results on the data sheet provided in