A4 Operating Sequence
Operating Sequence
The difference in the operating se-
quence of Versions 1 and 2 is primarily
due to when the slab is struck.
Both versions can be climbed with the
hydraulic self-climbing device
(Fig. A4.04) or by crane (Fig. A4.08).
Version 1
Climbing enclosure with straight protec-
tion screen.
The slab formwork can remain in posi-
tion. The climbing enclosure can climb
past the slab formwork.
Example
Operating sequence with shortened cy-
cle times if two sets of SKYDECK Slab
Formwork are used.
Step 1
Climbing enclosure is in position.
Close cover flaps.
Concrete the columns.
Step 2
Erect slab formwork with stopends.
Install leading anchor with the aid of the Slab An-
chor Template.
Fig. A4.01
Fig. A4.02