7
Initial operation
7.1
Checklist for initial operation
64
BiG Pack 1270
Original Operating Instructions 150000747_02_en
7
Initial operation
WARNING
Risk of injury or damage to the machine due to faulty initial operation
If the initial operation is carried out incorrectly or incompletely, the machine may present
defects. As a result, people may be injured or killed or the machine may be damaged.
Initial operation must only be carried out by authorised technicians.
Read in full and observe the “Personnel qualification of technicians”,
.
WARNING
Risk of injury due to non-observance of relevant safety instructions
If the relevant safety instructions are not observed, persons may be seriously injured or killed.
To avoid accidents, the relevant safety instructions must be read and observed,
WARNING
Risk of injury due to non-observance of safety instructions
If the relevant safety routines are not observed, persons may be seriously injured or killed.
The safety routines must be read and observed to avoid accidents,
.
7.1
Checklist for initial operation
ü
For "Hydraulic support jack" version: The hydraulic support jack is assembled,
.
ü
The height of the drawbar has been adjusted,
ü
The height of the drive train has been adjusted,
.
ü
The hydraulic system has been adjusted,
ü
The bale chute has been set,
.
ü
The fire extinguisher is mounted,
ü
All the screws and nuts have been checked to make certain they are tight and tightened to
the specified tightening torques,
.
ü
The oil level has been checked for all gearboxes,
.
ü
The machine has been fully lubricated,
.
ü
There are no leakages present in the machine.
ü
All cable and plug connections are properly connected and laid.
ü
All hoses are properly laid.
ü
The wheel chocks are at hand and ready to use,
.
ü
The tyres have been checked and the pressure is set correctly,
ü
The road travel lighting has been checked for function and cleanliness,