SAN140M Installation and Service Manual
32
6. Connect the remaining ends of the AC power cords to separate
(for redundancy) rack power strips.
NOTE:
The director does not have a power switch. Therefore the director
powers on when its power cords are connected to facility or rack power.
Figure 15
AC power connections (director)
7. Connect the equipment rack power cords to separate (for
redundancy) facility power sources that provide single-phase, 180
to 264 VAC voltage.
8. Power on the rack power strips.
9. Inspect the front panel of each rack-mounted Ethernet hub.
Ensure each green Power LED turns on.
10. The director powers on and performs POSTs. During POSTs:
— Amber LEDs on both CTP cards and all port cards illuminate
momentarily.
— The green LED on each CTP card (active and backup) and
each port card illuminate as the card is tested.
— Green LEDs associated with Fibre Channel ports sequentially
illuminate as the ports are tested.
11. After successful POST completion
— Bezel: POWER LED green
— Active CTP card: LED green
— Power supplies: PWR OK LEDs green
i140M018
Summary of Contents for TotalStorage SAN140M
Page 2: ......
Page 14: ...SAN140M Installation and Service Manual xii...
Page 16: ...SAN140M Installation and Service Manual xiv...
Page 54: ...SAN140M Installation and Service Manual 22...
Page 186: ...SAN140M Installation and Service Manual 154...
Page 240: ...SAN140M Installation and Service Manual 208...
Page 282: ...SAN140M Installation and Service Manual 250...
Page 294: ...SAN140M Installation and Service Manual 262...
Page 366: ...SAN140M Installation and Service Manual 334...
Page 370: ...SAN140M Installation and Service Manual 338...
Page 378: ...SAN140M Installation and Service Manual 346...
Page 424: ...SAN140M Installation and Service Manual 392...
Page 427: ......
Page 428: ...Printed in USA GC26 7664 04...