109
instrument down. The data
can be used to staking out roadway
immediately if needed.
10.2 Stake out (road)
You can used the inputted or imported LS files in staking
road way. When staking out roadway, you can select the desired
file any time for the demand so that staking out roadway with
any mileage can be done easily.
You may not be worried about the problem that the
capacity of 20 point of horizontal alignment and 20 point of
vertical alignment, because you can divide any long road into
several pieces and save them into several line type files.
Left deviation
Right deviation
520 Mileage
510
530
Mileage increment
Altitude difference(-)
Midcourt line
Midcourt line
Left deviation
Right deviation
The steps for staking out road way are as followed:
1)
Select [.LS] files for stake-out;
2)
Setup station;
3)
Setup BBS;
4)
Inputting Roadway parameters, including mileage of
“Start” (start mileage), “Space” (pile space), “L/R dist”
( left and right deviation) and “L/R dV” left and right
altitude difference (Left/Right dV);
5)
Then select center, left and right mileage to stake out.
6)
You may choose [Dist]—polar coordinates or [Coord.]