EBLA04~08E + EDLA04~08E
Daikin Altherma 3 M
ESIE22-09 – 2022.05
To check the wiring of the hydro PCB
Prerequisite:
First perform all earlier hydro PCB checks, see
175].
Prerequisite:
Stop the unit operation via the user interface.
Prerequisite:
Turn OFF the respective circuit breaker.
1
Check that all wires are properly connected and that all connectors are fully
plugged‑in.
2
Check that no connectors or wires are damaged.
3
Check that the wiring corresponds with the wiring diagram, see
INFORMATION
Correct the wiring as needed.
Is the problem solved?
Action
Yes
No further actions required.
No
Return to
175] of the hydro PCB
and continue with the next procedure.
To check the fuse of the hydro PCB
Prerequisite:
First perform all earlier hydro PCB checks, see
175].
1
Measure the continuity of the fuse. If no continuity is measured, the fuse has
blown.
a
a
Fuse
Blown fuse on the hydro PCB?
Action
Yes
Replace the blown fuse, see
No
Return to
175] of the hydro PCB
and continue with the next procedure.
draft – 31/05/2022 15:53