Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
501
Axis and Spindle Test Run
13
13.1
Requirements
Enabling signals must be set to allow an axis to be traversed directly from the control:
●
Drive: Parameters and terminals
●
NC: Interface signals
13.1.1
Drives: SINAMICS S120
Relevant parameters/terminals
Infeed
Parameter/Terminal
Description
p0840
ON/OFF1
p0844
1. OFF2
p0845
2. OFF2
p0852
Enable operation
X21.3 (+24 V) and X21.4 (ground)
EP terminals enable (pulse enable)
Drive
Parameter/Terminal
Description
p0840
ON/OFF1
p0844
1. OFF2
p0845
2. OFF2
p0848
1. OFF3
p0849
2. OFF3
p0852
Enable operation
X21.3 (+24 V) and X21.4 (ground)
EP terminals enable (pulse enable)
p0864
Infeed enable
p1140
Ramp-function generator enable
p1141
Ramp-function generator Start
p1142
Setpoint enable
References:
SINAMICS S120 Commissioning Manual
/GH2/ Equipment Manual for Booksize Power Units
Содержание SINUMERIK 840Di sl
Страница 118: ...Configuration 3 3 Connection overview Manual 118 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 148: ...Power On and Power Up 5 7 License management Manual 148 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 186: ...PLC commissioning 6 8 Load configuration in PG PLC STEP 7 Manual 186 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 344: ...Drive commissioning SINAMICS 9 5 Basic principles Manual 344 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 624: ...Glossary Manual 624 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...