Power-On and Power-Up
5.1 Preparing for commissioning
Manual
122
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
●
Function-impairing gases
●
Climatic environmental conditions
●
Storage/transport
●
Shock stressing
●
Vibratory load
●
Ambient temperature
5.1.2
Recommended sequence for first commissioning
Requirements
The individual steps for first commissioning are listed below in the recommended order.
1.
The whole plant is mechanically and electrically connected and tested for errors acc. to
the checklist (see previous section).
–
SINUMERIK 840Di sl
–
SINAMICS S120
References:
Guide for the SINUMERIK 840D sl machine configuring
–
SIMODRIVE 611 universal-converter system
–
Motors
–
SIMATIC S7 I/O components
–
HMI user interfaces
Note
Guidelines for machine configuration
The device manual "Guidelines for machine configuration SINUMERIK 840D sl"
currently refers only to SINUMERIK 840D sl with SINAMICS S120. The information
contained in this can, in principle, be applied to SINUMERIK 840Di sl with
SINAMICS S120. A revised edition for SINUMERIK 840Di sl is in preparation.
2.
The order numbers (MLFB) of the SIMODRIVE 611 universal drives and SIMATIC S7-I/O
components should be available. When creating the SIMATIC S7 project you must check,
whether the component chosen from the hardware catalog by "HW Config" corresponds
to the component used on the plant.
Содержание SINUMERIK 840Di sl
Страница 118: ...Configuration 3 3 Connection overview Manual 118 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 148: ...Power On and Power Up 5 7 License management Manual 148 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 186: ...PLC commissioning 6 8 Load configuration in PG PLC STEP 7 Manual 186 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 344: ...Drive commissioning SINAMICS 9 5 Basic principles Manual 344 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 624: ...Glossary Manual 624 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...