Drive commissioning (SINAMICS)
9.2 ONLINE commissioning
Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
331
9.2.15
Drive unit: Backing up parameters
After completing the configuration, you must load and save the parameters in the drive unit.
Implementation
Perform the following actions for each drive unit:
1.
Access the drive unit with the PG/PC online.
2.
Now load the project data into the drive unit: Right-click on Drive unit_Adr10 > Target unit
> Load to target system... in the project navigator.
3.
Save the project data in the drive unit on the CF card: Click on Drive unit_Adr10 > Target
unit > Copy RAM to ROM... in the project navigator.
9.2.16
Drive: Testing motor rotation
You can test the configuration loaded into the drive unit by running the motors of the drives
using the operator control panel in the STARTER.
Line/DC link identification will be carried out once the pulses for the infeed have been
enabled and line/DC link identification has been activated. The infeed then switches to
operational mode.
Note
For more information about the operator control panel: see SINAMICS S120 Getting Started
with the STARTER Commissioning Tool.
For more information about line/DC-link identification, see SINAMICS S120 Function
Manual.
Содержание SINUMERIK 840Di sl
Страница 118: ...Configuration 3 3 Connection overview Manual 118 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 148: ...Power On and Power Up 5 7 License management Manual 148 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 186: ...PLC commissioning 6 8 Load configuration in PG PLC STEP 7 Manual 186 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 344: ...Drive commissioning SINAMICS 9 5 Basic principles Manual 344 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 624: ...Glossary Manual 624 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...