NC Commissioning with HMI Advanced
11.11 NC/PLC Diagnosis
Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
487
–
4 startup
–
5 waiting for PLC
–
6 running
–
F NC error
●
NC Reset
Via the "NC reset" button, an NC POWER ON reset is triggered.
On a NC POWER ON reset, all active machining operations are stopped. Drives that are
in motion are not decelerated on their acceleration ramp but at that their current limit.
After startup, the NC is in the reset state. Machine and user data are not changed.
●
NC default data
Via the "NC Default Data" button, an NC POWER ON reset is triggered followed by NC
general reset. All active machining operations are stopped as described under "NC
Reset".
After startup, the NC is in the reset state. All machine and user data are deleted and
standard machine data are loaded.
NOTICE
After "NC Default Data" has been triggered, the NC must be commissioned again or a
series startup file read in (see Chapter "NC Default Data" (Page 541)).
●
Acknowledge alarm 4065
The following alarm is acknowledged via the "Acknowledge alarm 4065" button and an
NC POWER ON reset is initiated:
–
Alarm "4065 Battery-backed memory has been restored from back-up copy (possible
data loss!)".
To acknowledge the alarm via softkey, it is first necessary to switch to the follow-up
softkey bar with the "ETC" key.
Note
Alarm 4065 is also acknowledged by NC POWER ON reset via "NC Default Data".
Then the NC must be commissioned again or a series startup file read in (see Chapter
"Application data backup/series startup" (Page 541)).
Group: PLC
The following functions are grouped together in the PLC group box:
●
PLC RUN-P
With the "PLC RUN-P" button, the PLC is put in the "RUN-PROGRAMMING" state. In this
operating state, changes can be made to the PLC user program without activation of the
password.
●
PLC RUN
Содержание SINUMERIK 840Di sl
Страница 118: ...Configuration 3 3 Connection overview Manual 118 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 148: ...Power On and Power Up 5 7 License management Manual 148 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 186: ...PLC commissioning 6 8 Load configuration in PG PLC STEP 7 Manual 186 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 344: ...Drive commissioning SINAMICS 9 5 Basic principles Manual 344 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...
Страница 624: ...Glossary Manual 624 Commissioning Manual 05 2008 6FC5397 4CP10 4BA0 ...