Foundation requirements
Requirements
• The foundation must be able to absorb any type of vibration and form a permanent, rigid support for
the unit.
• The location and size of the foundation bolt holes must match those shown on the assembly drawing
provided with the pump data package.
• The foundation must weigh between two and three times the weight of the pump.
• Provide a flat, substantial concrete foundation in order to prevent strain and distortion when you
tighten the foundation bolts.
• Sleeve-type and J-type foundation bolts are most commonly used. Both designs allow movement for
the final bolt adjustment.
Sleeve-type bolts
1
2
3
4
5
6
1.
Baseplate
2.
Shims or wedges
3.
Foundation
4.
Sleeve
5.
Dam
6.
Bolt
J-type bolts
1
3
2
4
5
1.
Baseplate
2.
Shims or wedges
3.
Foundation
4.
Dam
5.
Bolt
Baseplate-mounting procedures
Prepare the baseplate for mounting
1. Remove all the attached equipment from the baseplate.
2. Clean the underside of the baseplate completely.
3. If applicable, coat the underside of the baseplate with an epoxy primer.
Use an epoxy primer only if you used an epoxy-based grout.
4. Remove the rust-proofing coat from the machined mounting pads using an appropriate solvent.
5. Remove water and debris from the foundation-bolt holes.
Installation
Model HT 3196 i-FRAME Installation, Operation, and Maintenance Manual
21
Содержание HT 3196 i-FRAME
Страница 1: ...Goulds Pumps Installation Operation and Maintenance Manual Model HT 3196 i FRAME ...
Страница 2: ......
Страница 140: ...Certification CE or CE ATEX 138 Model HT 3196 i FRAME Installation Operation and Maintenance Manual ...
Страница 141: ...ATEX notification Certification CE or CE ATEX Model HT 3196 i FRAME Installation Operation and Maintenance Manual 139 ...
Страница 143: ...Certification CE or CE ATEX Model HT 3196 i FRAME Installation Operation and Maintenance Manual 141 ...
Страница 147: ......