If the pump size is... Then...
XLT-i
1. Align the end plate on the pump side to the bearing housing so that
you meet these conditions:
a.
The large slots on the end plate do not touch the bearing housing
tap bolts.
b. The small slots align with the impeller adjusting bolts.
2. Fasten the end plate to the bearing housing using the jam nuts on the
impeller adjusting bolts.
3. Check the impeller clearance. Refer to the impeller clearance table for
the correct impeller clearance.
1
2
3
4
1.
Driver
2.
Pump end plate
3.
Bearing housing
4.
Jam nut
3. Put the pump-half of the coupling guard in place:
a) Slightly spread the bottom apart.
b) Place the coupling guard half over the pump-side end plate.
Commissioning, Startup, Operation, and Shutdown
Model HT 3196 i-FRAME Installation, Operation, and Maintenance Manual
47
Содержание HT 3196 i-FRAME
Страница 1: ...Goulds Pumps Installation Operation and Maintenance Manual Model HT 3196 i FRAME ...
Страница 2: ......
Страница 140: ...Certification CE or CE ATEX 138 Model HT 3196 i FRAME Installation Operation and Maintenance Manual ...
Страница 141: ...ATEX notification Certification CE or CE ATEX Model HT 3196 i FRAME Installation Operation and Maintenance Manual 139 ...
Страница 143: ...Certification CE or CE ATEX Model HT 3196 i FRAME Installation Operation and Maintenance Manual 141 ...
Страница 147: ......