GE H
EALTHCARE
D
IRECTION
5213326-100, R
EVISION
3
LOGIQ™ A3 S
ERVICE
M
ANUAL
3-14
Section 3-4 - Completing the Installation
3-4-4
Power On / Off Process
NOTE:
After turning off a system, wait at least ten seconds before turning it on again. The system may not be
able to boot if power is recycled too quickly.
3-4-4-1
Scanner Power On
1.) Connect the Power Cable to the back of the system.
2.) Connect the Main Power Cable to a hospital grade power receptacle with the proper rated voltage.
Never use an adapter that would defeat the safety ground.
3.) Switch ON the Circuit Breaker at the rear of the system.
A- Circuit Breaker
B- Power cable
When power is applied to the scanner and the rear Circuit Breaker is turned ON, power is distributed to
the Transformer Assembly
Figure 3-8 Circuit Breaker and Power Cable on Back of Scanner
A
B
State: RELEASE - Document is released and under formal Change Control. Changes are subject to the ECR/ECO Process.
See the GEHC Myworkshop System to determine the status of this document.
Approved Document - 5213326-100TPH_r3.pdf Page 71 of 252