GE H
EALTHCARE
D
IRECTION
5213326-100, R
EVISION
3
LOGIQ™ A3 S
ERVICE
M
ANUAL
3-16
Section 3-4 - Completing the Installation
3-4-5
Power Off/ Shutdown
NOTE:
After turning off a system, wait at least ten seconds before turning it on again. The system may
not be able to boot if power is recycled too quickly.
3-4-5-1
System Power Down
To power off the system:
1.) Lightly press the
Power On/Off
switch at the front of the system once. The Shutdown window
is displayed.
NOTE:
DO NOT press and hold down the Power On/Off switch to shutdown the system. Instead, lightly
press the Power On/Off switch and select Shutdown.
2.) Using the Trackball, select Shutdown.
The shutdown process takes a few seconds and is completed when the control panel
illumination shuts down.
3.) Disconnect the probes.
Clean or disinfect all probes as necessary. Store them in their shipping cases to avoid
damage.
4.) If daily maintenance is to be performed, turn off the circuit breaker.
NOTE:
Do not pull the power cable without turning off the circuit breaker.
(or)
1.) Press the
Power On/Off
switch on the Control Panel , and hold it till power goes off from the
system.
CAUTION
DO NOT turn off the circuit breaker before the Power On/Off switch LED is
amber.
Data may be lost or system software damaged if the circuit breaker is turned off
before the Power On LED is amber.
State: RELEASE - Document is released and under formal Change Control. Changes are subject to the ECR/ECO Process.
See the GEHC Myworkshop System to determine the status of this document.
Approved Document - 5213326-100TPH_r3.pdf Page 73 of 252