Commissioning
Proline Cubemass C 300
114
Hauser
Parameter overview with brief description
Parameter
Description
Selection / User interface
Factory setting
Process conditions
Ensure process conditions as follows.
• Tubes are completely filled
• Process operational pressure
applied
• No-flow conditions (closed
valves)
• Process and ambient
temperatures stable
–
Progress
Shows the progress of the process.
0 to 100 %
–
Status
Shows the status of the process.
• Busy
• Failed
• Done
–
Abort cause
Indicates why the wizard was aborted.
• Check process conditions!
• A technical issue has
occurred
–
Root cause
Shows the diagnostic and remedy.
• Zero point too high. Ensure
no-flow.
• Zero point is unstable.
Ensure no-flow.
• Fluctuation high. Avoid 2-
phase medium.
–
Reliability of measured zero point
Indicates the reliability of the zero point
measured.
• Not done
• Good
• Uncertain
–
Additional information
Indicate whether to display additional
information.
• Hide
• Show
Hide
Zero point measured
Shows the zero point measured for the
adjustment.
Signed floating-point number
–
Zero point standard deviation
Shows the standard deviation of the zero
point measured.
Positive floating-point number –
Select action
Select the zero point value to apply.
• Keep current zero point
• Apply zero point measured
• Apply factory zero point
Keep current zero point
*
Visibility depends on order options or device settings
10.5.4 Configuring the totalizer
In the
"Totalizer 1 to n" submenu
the individual totalizer can be configured.
Navigation
"Setup" menu → Advanced setup → Totalizer 1 to n
‣
Totalizer 1 to n
Assign process variable
Unit totalizer 1 to n
Totalizer operation mode
Failure mode