Inteli NT MINT, SW Version 2.6, ©ComAp – November 2011
IGS-NT-MINT-2.6-Reference Guide.PDF
9
6)
If total load increases and selected
LoadRes strt
is no more fulfilled, after a
Next start del
next ready
gen-set with the highest priority (lowest priority number) is started and synchronized to the bus.
7)
If load decreases and selected
LoadRes stp
is exceeded, after a
Next stop del
the running gen-set with
the lowest priority is unloaded, got off line, cooled and stopped.
8) Complete gen-sets group stops when binary input SYS START/STOP opens. If the input MCB
FEEDBACK is closed (gen-sets are in parallel to mains) controllers softly transfer the load to the mains.
When gen-set is unloaded (see
GCB open level
or
GCB open del
) opens the output GCB
CLOSE/OPEN.
9) The Running hours balancing or Load demand engines swap can be activated in power management.
Hint:
Controller does not respond to GCB ON/OFF , STOP, START buttons and corresponding remote
InteliMonitor or Modbus commands in AUT mode.
Set
Basic setting
:
FltRes GoToMAN
= ENABLED to avoid automatic engine start when pressing FAULT
RESET after any 2
nd
level alarm (Shutdown, Slow stop, Breaker Open&Cooldown).