17-21
Cisco ONS 15454 Procedure Guide, R5.0
March 2005
Chapter 17 DLPs A1 to A99
DLP-A18 Turn On and Verify Office Power
Note
When terminating battery and battery return connections as shown in
, follow a
torque specification of 10 in-lb (0.12 m-kg).
Step 7
Terminate the return 1 lead to the RET1 backplane terminal. Use oxidation prevention grease to keep
connections noncorrosive.
Warning
Do not secure multiple connectors with the same bolt assembly.
Step 8
Terminate the negative 1 lead to the negative BAT1 backplane power terminal. Use oxidation prevention
grease to keep connections noncorrosive.
Step 9
If you use redundant power leads, terminate the return 2 lead to the positive RET2 terminal on the
ONS 15454. Terminate the negative 2 lead to the negative BAT2 terminal on the ONS 15454. Use
oxidation prevention grease to keep connections noncorrosive.
Step 10
Route the cables out below the power terminals using the plastic cable clamp, as shown in
Step 11
Return to your originating procedure (NTP).
DLP-A18 Turn On and Verify Office Power
Step 1
Using a voltmeter, verify the office battery and ground at the following points on the fuse and alarm
panel:
a.
To verify the power, place the black test lead of the voltmeter to the frame ground. Place the red test
lead on the A-side connection and verify that it is between –40.5 VDC and –57 VDC. Place the red
test lead on the B-side connection and verify that it is between –40.5 VDC and –57 VDC.
Note
The voltages –40.5 VDC and –57 VDC are, respectively, the minimum and maximum
voltages required to power the chassis.
b.
To verify the ground, place the black test lead of the voltmeter to the frame ground. Place the red
test lead on the A-side return ground and verify that no voltage is present. Place the red test lead on
the B-side return ground and verify that no voltage is present.
Step 2
Complete one of the following to power up the node:
•
If you are using a 80-A fuse panel, insert a 20-A fuse into the fuse position according to site practice.
Purpose
This task measures the power to verify correct power and returns.
Tools/Equipment
Voltmeter
Prerequisite Procedures
DLP-A16 Connect the Office Ground to the ONS 15454, page 17-18
DLP-A17 Connect Office Power to the ONS 15454 Shelf, page 17-19
Required/As Needed
Required
Onsite/Remote
Onsite
Security Level
None
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...