5-30
Cisco ONS 15454 Procedure Guide, R5.0
December 2004
Chapter 5 Turn Up Network
NTP-A209 Provision an Integrated BLSR/Path Protection Dual-Ring Interconnect
NTP-A209 Provision an Integrated BLSR/Path Protection
Dual-Ring Interconnect
Step 1
Complete the
“DLP-A60 Log into CTC” task on page 17-66
at a node in the BLSR and path protection
DRI network. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the BLSR and path protection that you will
interconnect in an integrated DRI. If the BLSR and path protection are created, continue with Step
.
a.
To provision and test the BLSR, complete the following:
•
“NTP-A40 Provision BLSR Nodes” procedure on page 5-10
•
“NTP-A126 Create a BLSR” procedure on page 5-12
•
“NTP-A175 Two-Fiber BLSR Acceptance Test” procedure on page 5-13
•
“NTP-A176 Four-Fiber BLSR Acceptance Test” procedure on page 5-15
b.
To provision and test the path protection, complete the following:
•
“NTP-A44 Provision Path Protection Nodes” procedure on page 5-20
•
“NTP-A177 Path Protection Acceptance Test” procedure on page 5-22
Step 3
Verify that the BLSR and path protection DRI interconnect nodes have OC-N cards installed and have
fiber connections to the other interconnect node:
•
The OC-N cards that will connect the BLSR and path protection must be installed at the interconnect
nodes. The OC-N cards in the path protection nodes and the interconnect nodes must be the same
type.
•
The interconnect nodes must have the correct fiber connections. An example is shown in
.
Purpose
This procedure provisions a BLSR and a path protection in an integrated
DRI topology.
Tools/Equipment
None
Prerequisite Procedures
NTP-A35 Verify Node Turn-Up, page 5-2
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Provisioning and higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...