Cisco ONS 15454 Procedure Guide, R5.0
December 2004
Chapter 13 Convert Network Configurations
NTP-A154 Convert a 1+1 Point-to-Point to a Linear ADM Manually
NTP-A154 Convert a 1+1 Point-to-Point to a Linear ADM
Manually
Note
Optical transmit and receive levels should be in their acceptable range as shown in the specifications
section for each card in
.
Note
In a point-to-point configuration, two OC-N cards are connected to two OC-N cards on a second node.
The working OC-N ports have data communications channel (DCC) terminations, and the OC-N cards
are in a 1+1 protection group.
Step 1
Complete the
“DLP-A60 Log into CTC” task on page 17-66
at one of the two point-to-point nodes. If
you are already logged in, continue with Step 2.
Step 2
Complete the
“DLP-A298 Check the Network for Alarms and Conditions” task on page 19-63
.
Step 3
Log into the node that will be added to the point-to-point configuration (the new node).
Note
If you are attempting to add an unreachable node you must first log in to the unreachable node
using a separate CTC session and configure that node. Delete any existing protection groups as
described in
“DLP-A155 Delete a Protection Group” task on page 18-23
. Delete any existing
DCC terminations as described in the
“DLP-A156 Delete a Section DCC Termination” task on
or the
“DLP-A359 Delete a Line DCC Termination” task on page 20-45
Step 4
Complete the
“NTP-A24 Verify Card Installation” procedure on page 4-2
to ensure that the new node
has two OC-N cards with the same rate as the point-to-point nodes.
Step 5
Complete the
“NTP-A35 Verify Node Turn-Up” procedure on page 5-2
for the new node.
Step 6
Physically connect the fibers between the point-to-point node and the new node. The fiber connections
should be connected from working card to working card and protect card to protect card.
Step 7
On the new node, create a 1+1 protection group for the OC-N cards in the point-to-point node that will
connect to the point-to-point node. See the
“DLP-A73 Create a 1+1 Protection Group” task on
.
Purpose
This procedure upgrades a 1+1 point-to-point configuration (two nodes)
to a linear ADM configuration (three or more nodes) manually, that is,
without using the in-service topology upgrade wizard. Use this
procedure if the wizard is unavailable or if you need to back out of the
wizard.
Tools/Equipment
None
Prerequisite Procedures
NTP-A124 Provision a Point-to-Point Network, page 5-3
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Provisioning or higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...