19-29
Cisco ONS 15454 Procedure Guide, R5.0
September 2005
Chapter 19 DLPs A200 to A299
DLP-A246 Provision E-Series Ethernet Card Mode
DLP-A246 Provision E-Series Ethernet Card Mode
Caution
You cannot change the mode while the Ethernet card is carrying circuits. If you want change the card
mode, delete any circuits that it carries first. See the
“NTP-A278 Modify and Delete Overhead Circuits”
Step 1
In the network view, double-click the node containing the E-Series Ethernet card you want to provision,
then double-click the Ethernet card.
Step 2
Click the
Provisioning > Card
tabs.
Step 3
In the Card Mode area, choose one of the following:
•
For multicard EtherSwitch circuit groups, choose
Multicard EtherSwitch Group
.
•
For single-card EtherSwitch circuits, choose
Single-card EtherSwitch
.
•
For port-mapped circuits, choose
Port-mapped
.
Step 4
Click
Apply
.
Step 5
If you are using multicard EtherSwitch circuits, repeat Steps
through
for all other Ethernet cards in
the node that will carry the multicard EtherSwitch circuits.
Step 6
Repeat Steps
through
for other nodes as necessary.
Step 7
Return to your originating procedure (NTP).
DLP-A247 Change an OC-N Card
Purpose
This task provisions an E-Series Ethernet card for multicard EtherSwitch
Group, single-card EtherSwitch, or port-mapped mode.
Tools/Equipment
E-Series Ethernet cards (E100T-12/E100T-G, E1000-2/E1000-2-G) must
be installed.
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Provisioning or higher
Purpose
This task changes an OC-N card while maintaining existing provisioning,
including data communications channels (DCCs), circuits, protection,
timing, and rings. This task is intended to be used when a slot is
preprovisioned and you want to change the optical speed of the card, or
when you have backed out of an automatic span upgrade.
Tools/Equipment
None
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Provisioning or higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...