6-36
Cisco ONS 15454 Procedure Guide, R5.0
August 2005
Chapter 6 Create Circuits and VT Tunnels
NTP-A135 Test Electrical Circuits
Step 18
Verify that the VAP you just created appears in the circuits list. VAPs are identified in the Type column.
The VAP tunnel automatically transitions into the IS-NR service state.
Stop. You have completed this procedure.
NTP-A135 Test Electrical Circuits
Step 1
Complete the
“DLP-A60 Log into CTC” task on page 17-66
at the node where you want to test the
electrical circuits. If you are already logged in, continue with
.
Step 2
From the View menu, choose
Go to Network View
.
Step 3
Click the
Circuits
tab.
Step 4
Complete the
“DLP-A230 Change a Circuit Service State” task on page 19-19
to set the circuit and
circuit ports to the maintenance service state (OOS-MA,MT). Take note of the original state because you
will return the circuit to that state later.
Step 5
Set the source and destination DS1 or DS3 card line length:
a.
In network view, double-click the source node.
b.
Double-click the circuit source card and click the
Provisioning > Line
tabs.
c.
From the circuit source port Line Length drop-down list, choose the line length for the distance (in
feet) between the DSX (if used) or circuit termination point and the source ONS 15454.
d.
Click
Apply
.
Purpose
This procedures tests DS-1 and DS-3 circuits.
Tools/Equipment
A test set and all appropriate cables
Prerequisite Procedures
This procedure assumes you completed a facility loopback tests on the
fibers and cables from the source and destination ONS 15454s to the digital
signal cross-connect (DSX), and that you created a circuit using one of the
following procedures:
NTP-A139 Create a Half Circuit on a BLSR or 1+1 Node, page 6-52
NTP-A140 Create a Half Circuit on a Path Protection Node, page 6-54
NTP-A181 Create an Automatically Routed DS-1 Circuit, page 6-6
NTP-A182 Create a Manually Routed DS-1 Circuit, page 6-11
NTP-A183 Create a Unidirectional DS-1 Circuit with Multiple Drops,
page 6-14
NTP-A184 Create an Automatically Routed DS-3 Circuit, page 6-18
NTP-A185 Create a Manually Routed DS-3 Circuit, page 6-23
NTP-A186 Create a Unidirectional DS-3 Circuit with Multiple Drops,
page 6-25
Required/As Needed
Required
Onsite/Remote
Onsite
Security Level
Provisioning or higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...