Chapter 5 Turn Up Network
NTP-A173 Point-to-Point Network Acceptance Test
Step 4
Verify that the working and protect cards in the 1+1 protection groups correspond to the physical fiber
connections between the nodes, that is, verify that the working card in one node connects to the working
card in the other node, and that the protect card in one node connects to the protect card in the other node.
Step 5
Complete the
“DLP-A377 Provision Section DCC Terminations” task on page 20-61
for the working
OC-N port on both point-to-point nodes. Alternatively, if additional bandwidth is needed for CTC
management, complete the
“DLP-A378 Provision Line DCC Terminations” task on page 20-62
Note
DCC terminations are not provisioned on the protect ports.
Note
If the point-to-point nodes are not connected to a LAN, you will need to create the DCC
terminations using a direct (craft) connection to the node. Remote provisioning is possible only
after all nodes in the network have DCC terminations provisioned to in-service OC-N ports.
Step 6
Complete the
“DLP-A214 Change the Service State for a Port” task on page 19-9
to put the protect card
in-service.
Step 7
As needed, complete the
“DLP-A380 Provision a Proxy Tunnel” task on page 20-63
Step 8
As needed, complete the
“DLP-A381 Provision a Firewall Tunnel” task on page 20-64
.
Step 9
As needed, complete the
“DLP-A367 Create a Provisionable Patchcord” task on page 20-51
.
Step 10
Verify that timing is set up at both point-to-point nodes. If not, complete the
for one or both of the nodes. If a node uses line timing, make its working OC-N
card the timing source. The system will automatically choose the corresponding protect OC-N card as
the protect timing source. This will be visible in the Maintenance > Timing tab.
Step 11
Complete the
“NTP-A173 Point-to-Point Network Acceptance Test” procedure on page 5-4
Stop. You have completed this procedure.
NTP-A173 Point-to-Point Network Acceptance Test
Caution
This procedure might be service affecting if performed on a node carrying traffic.
Step 1
Complete the
“DLP-A60 Log into CTC” task on page 17-66
at one of the point-to-point nodes. The node
(default) view appears. If you are already logged in, continue with Step 2.
Step 2
From the View menu, choose
Go to Network View
.
Purpose
This procedure tests a point-to-point network.
Tools/Equipment
Test set/cables appropriate to the test circuit you will create
Prerequisite Procedures
NTP-A124 Provision a Point-to-Point Network, page 5-3
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Provisioning and higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...