DLP-A378 Provision Line DCC Terminations
Note
DCC Termination Failure (EOC) and Loss of Signal (LOS) alarms appear until you create all
network DCC terminations and put the DCC termination OC-N ports in service.
Step 8
Return to your originating procedure (NTP).
DLP-A378 Provision Line DCC Terminations
Note
When LDCC is provisioned, an SDCC termination is allowed on the same port, but is not recommended.
Using SDCC and LDCC on the same port is only needed during a software upgrade if the software
version does not support LDCC. You can provision SDCCs and LDCCs on different ports in the same
node.
Step 1
In node view, click the
Provisioning > Comm Channels > LDCC
tabs.
Step 2
Click
Create
.
Step 3
In the Create LDCC Terminations dialog box, click the ports where you want to create the LDCC
termination. To select more than one port, press the Shift key or the Ctrl key.
Note
LDCC is used for ONS 15454 DCC terminations. The SONET LDCCs and the SDCC (when not
used as a DCC termination by the ONS 15454) can be provisioned as DCC tunnels. See the
“DLP-A313 Create a DCC Tunnel” task on page 20-7
.
Step 4
In the Port Admin State area, click
Set to IS
to put the port in service.
Step 5
Verify that the Disable OSPF on DCC Link check box is unchecked.
Step 6
If the SDCC termination is to include a non-ONS node, check the
Far End is Foreign
check box. This
automatically sets the far-end node IP address to 0.0.0.0, which means that any address can be specified
by the far end. To change the default to a specific the IP address, see the
Termination” task on page 20-60
Step 7
Click
OK
.
Purpose
This task creates the LDCC terminations required for administration data,
alarms, signal control information, and messages. LDCCs are three times
larger than SDCCs. In this task, you can also set up the node so that it has
direct IP access to a far-end non-ONS node over the DCC network.
Tools/Equipment
None
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Provisioning or higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...