Cisco ONS 15454 Procedure Guide, R5.0
March 2005
Chapter 17 DLPs A1 to A99
DLP-A17 Connect Office Power to the ONS 15454 Shelf
Step 3
Dress the power according to local site practice.
Warning
When installing or replacing the unit, the ground connection must always be made first and
disconnected last.
Statement 202
Figure 17-10
Cisco ONS 15454 Power Terminals
Step 4
Remove or loosen the #8 power terminal screws on the ONS 15454. To avoid confusion, label the cables
connected to the BAT1/RET1 (A) power terminals as 1, and the cables connected to the BAT2/RET2 (B)
power terminals as 2.
Note
Use only pressure terminal connectors, such as ring and fork types, when terminating the battery,
battery return, and frame ground conductors.
Caution
Before you make any crimp connections, coat all bare conductors (battery, battery return, and
frame ground) with an appropriate antioxidant compound. Bring all unplated connectors,
braided strap, and bus bars to a bright finish, then coat with an antioxidant before you connect
them. You do not need to prepare tinned, solder-plated, or silver-plated connectors and other
plated connection surfaces, but always keep them clean and free of contaminants.
Caution
When terminating power, return, and frame ground, do not use soldering lug, screwless
(push-in) connectors, quick-connect, or other friction-fit connectors.
Step 5
Strip 1/2 inch (12.7 mm) of insulation from all power cables that you will use.
Step 6
Crimp the lugs onto the ends of all power leads.
33921
RET 1
CAUTION: Remove power from both
the BAT1 and terminal blocks
prior to servicing
SUITABLE FOR MOUNTING ON
A NON-COMBUSTIBLE SURFACE.
PLEASE REFER TO INSTALLATION
INSTRUCTIONS.
-42 V 24 A
BAT 1
RET 2
BAT 2
Battery leads (red)
Return leads (black)
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...