APPENDIX B - DAILY CNG AND CNG WITH RECOVERY MODE
B-17
D
AILY
Printed 603.95.241
Base - 02/2012
Operations on the system
B.3.7
Repair interventions on fittings and pipes
If gas leaks occur from the pipe or fittings, replace the pipe assembly. The pipe is not provided with the fittings and these must
be obtained separately.
•
Remove the pipe to be replaced together with its end fittings.
•
Check the condition of the new pipe that is pre-formed into the same configuration as the pipe to be replaced and fit new fittings
and o-rings at its ends.
•
Fit the pipe by fitting its ends into the seats of the components to be connected and ensure that they are fitted fully home.
•
Check the pipe end centre line is aligned with the centre line of the fitting to which it is to be connected to prevent pretensioning.
•
Pre-tighten the fitting nuts by and then tighten to the specified torque. For EMER fittings, follow the procedure described in the
relevant chapter.
•
Apply the fastening brackets checking that the tube is not subjected to excessive tension.
•
Restore system operation by carrying out a hydraulic seal test following the procedure described in the warnings at the beginning
of the chapter.
Fitting assembly
Figure B.18
118974
•
Fit the seals (2 and 3) on the pipe.
•
Insert the pipe (5) in the valve seat (1), appropriately orienting the cylinder to avoid pulling the pipe.
•
Keeping the pipe in the seat, fasten the fitting (4) at the specified torque.
•
Loosen the fitting (4) and check fastening of the seal on the pipe.
•
Fasten the fitting at the specified torque.
•
Have the system hydraulically tested as indicated in the warnings at beginning of the chapter.
In case of subsequent disassembly, replace the seals with new parts.
NOTE
Summary of Contents for DAILY M.Y. 2012
Page 1: ...DAILY M Y 2012 BODYBUILDERS INSTRUCTIONS L I G H T R A N G E ISSUE 2012 ...
Page 4: ...Base 02 2012 Printed 603 95 241 Update data ...
Page 8: ...Index of section Base 02 2012 Printed 603 95 241 ...
Page 10: ...1 2 GENERAL SPECIFICATIONS DAILY Base 02 2012 Printed 603 95 241 Index ...
Page 26: ...1 18 GENERAL SPECIFICATIONS DAILY Base 02 2012 Printed 603 95 241 Convention ...
Page 30: ...2 4 CHASSIS MODIFICATIONS DAILY Base 02 2012 Printed 603 95 241 Index ...
Page 98: ...2 72 CHASSIS MODIFICATIONS DAILY Base 02 2012 Printed 603 95 241 Chocks ...
Page 140: ...4 2 POWER TAKE OFFS DAILY Base 02 2012 Printed 603 95 241 Index ...
Page 214: ...A 2 APPENDIX A DAILY PASSENGER TRANSPORT DAILY Base 02 2012 Printed 603 95 241 Index ...