Section 75
00-02-0878
2013-03-07
- 99 -
Nominal Settings
How to Change the Nominal Settings
The nominal settings can be changed to match different voltages and frequencies. The
EMS-GC10 has four sets of nominal values for the generator, and they are adjusted in
parameters.
EMS-GC10 Nominal Settings
Parameters
1
6001–6005
2
6011–6015
3
6021–6025
4
6031–6035
There are also two sets of nominal settings for the busbar, they can be adjusted in
parameters.
Busbar Nominal Settings
Parameters
1
6051–6053
2
6061–6063
NOTE:
If no busbar voltage transformer is present, the primary and
secondary side values are set to generator nominal value.
NOTE:
The possibility to switch between the four sets of nominal
set points is typically used on rental gensets, where switching
between 50 and 60 Hz is required, or switching between different
generator tapping or steering (single phase, three phase, 208/120,
480, ect.
Activation
The switching between the nominal set points, for the generator, can be done in two
ways; digital input & parameter 6006. Switching between busbar parameters sets is
done in parameter 6054.
Digital Input
M-Logic is used when a digital input is needed for switching between the four sets of
nominal settings. Select the required input among the input events, and select the
nominal settings in the outputs.
Example:
Event A
Event B
Event C
Output
Dig. input no. 10
or
Not used
or
Not used
Set nom. parameter settings 1
Not Dig. input no. 10
or
Not used
or
Not used
Set nom. parameter settings 2
Summary of Contents for EMS-GC10
Page 1: ...00 02 0878 Section 75 2013 03 07 GensetControllerUnit ModelEMS GC10 Operator sManual ...
Page 14: ...Section 75 00 02 0878 2013 03 07 8 Menu Structure Diagram ...
Page 33: ...Section 75 00 02 0878 2013 03 07 27 MB Open Sequence ...
Page 34: ...Section 75 00 02 0878 2013 03 07 28 GB Open Sequence ...
Page 35: ...Section 75 00 02 0878 2013 03 07 29 Stop Sequence ...
Page 36: ...Section 75 00 02 0878 2013 03 07 30 Start Sequence ...
Page 37: ...Section 75 00 02 0878 2013 03 07 31 MB Close Sequence ...
Page 38: ...Section 75 00 02 0878 2013 03 07 32 GB Close Sequence ...
Page 39: ...Section 75 00 02 0878 2013 03 07 33 Load Takeover LTO ...
Page 40: ...Section 75 00 02 0878 2013 03 07 34 Island Operation ...
Page 41: ...Section 75 00 02 0878 2013 03 07 35 Automatic Mains Failure AMF ...
Page 42: ...Section 75 00 02 0878 2013 03 07 36 Test Sequence ...
Page 48: ...Section 75 00 02 0878 2013 03 07 42 Stop Sequence The drawings illustrate the stop sequence ...
Page 74: ...Section 75 00 02 0878 2013 03 07 68 Start ...